Initial public release. Companion to cpp-cpm-engine and cpp-xer-parser.
Features
- Nine-check critical path validator (
validate_critical_path): CP identification, constraint-driven criticality, open ends, relationship quality, lag analysis, out-of-sequence progress, near-critical paths, logic continuity, constraint saturation. - CP Confidence Score — weighted across all 9 checks (0-100).
- HTML dashboard output with RAG status grid, CP / near-critical / open-ends tables.
- DCMA 14-Point Assessment with three bundled profiles (commercial, nuclear, mining).
- Driving path tracer — walks driving-predecessor chains for any activity.
- BEI / CPLI — NDIA PASEG §10 and DCMA #14 indices.
- LPM-confirmed false-CP detection — Check 2 surfaces TFM-flagged activities that LPM rejects from the longest path (requires
cpp-cpm-engine; degrades gracefully when absent).
Engine compatibility
Tested against cpp-cpm-engine v2.9.x (current as of 2026-05-16: v2.9.11+). Check 2 LPM cross-check requires the engine on PYTHONPATH; CI now clones the engine and exercises the LPM-confirmed-false-CP detection on every push.
CI hardening (v0.1.0 release infra)
- LPM test no longer silently skipped on CI — engine is cloned and the headline differentiator is exercised on 9 jobs (3 OSes × 3 Python versions).
- Drift check fails the build if the bundled
scripts/xer_parser.pydiverges fromcpp-xer-parser/main.
Security
See SECURITY.md — 90-day coordinated disclosure, hello@criticalpathpartners.ca with SECURITY in the subject.
See CHANGELOG.md for the full v0.1.0 entry.