Activities to be planned

...

Mon 24-7 (day -10)

  • Deploy core + WiFi controllers on-site
  • Deploy AP on top of L0
  • Staging

Tue 25-7 (day -9)

  • Staging
  • Orga on-site (in the night)

Wed 26-7 (day -8)

Thu 27-7 (day -7)

  • Staging
  • CCC flightcase arrives?
  • NOC storage available & Logistics team on-site (to be confirmed)

Fri 28-7 (day -6)

  • NOC tent setup
  • Delivery of generators E0 + L0
  • Delivery of airco's
  • Build base of operations
  • Transport of gear/cables to site
  • NOC storage available & Logistics team on-site (to be confirmed)
  • Scafftubes arrive

Sat 29-7 (day -5)

  • Rollout orga area
  • Start datenklo deployment
  • Start cable deployment
    • Fibres to DK-Uplink-*, entrance and parkinglot have priority
  • POC arrives
  • SysAdmin deploy servers

Sun 30-7 (day -4)

  • Continue cable deployment
    • Fibres to DK-Uplink-*, entrance and parkinglot have priority

Mon 31-7 (day -3)

  • Continue cable deployment
  • Start access deployment (if power is done)
    • Entrance & parking lot have priority

Tue 1-8 (day -2)

  • Continue access deployment
    • Entrance & parking lot have priority

Wed 2-8 (day -1)

  • Continue access deployment
  • EOD: finish deployment

Thu 3-8 (day 0)

  • Stuff should be done, time for relaxing

Fri 4-8 (day 1)

  • Day 1

Sat 5-8 (day 2)

  • Day 2

Sun 6-8 (day 3)

  • Day 3

Mon 7-8 (day 4)

  • Day 4

Tue 8-8 (day 5 + teardown day 0)

  • Day 5
  • Start teardown

Wed 9-8 (teardown day 1)

  • Teardown

Thu 10-8 (teardown day 2)

  • Finish NOC teardown

Fri 11-8 (teardown day 3)

  • Overflow
  • Pickup datenklos
  • Pickup of aircos
  • Pickup of telehandler
  • Pickup of generators

Past events

Sat 3-6

  • From 17:00 - Hackaton with Cumulus gear @ Bitlair

Sun 4-6

  • From 11:00 - Hackaton with Cumulus gear @ Bitlair

Sat 24-6

Sun 25-6

  • Cumulus hacking @ Bitlair

Week of 3-7

  • Deploy uplink gear @ Nikhef (Juniper)

Wed 5-7

  • NOC meeting 21:00 @ Mumble

Sat 8-7

Sun 9-7

  • Finishing up of fibres

Sat 15-7

  • Testing of on-field patches, meet @ 11:30 @ Bitlair

Sun 16-7

  • Staging @ Bitlair (core)

Tue 18-7

  • Building of AP boxes

Sat 22-7

  • Deadline for EuroFiber/Unet dark-fibre
  • Deploy uplink gear @ Zeewolde, meet @ 11:30 @ Bitlair
  • Deploy core-gear @ Zeewolde, meet @ 11:30 @ Bitlair
  • Staging party @ Bitlair (access, WiFi)

Sun 23-7

  • Staging