- Deploy core + WiFi controllers on-site
- Deploy AP on top of L0
- Staging
- Staging
- Orga on-site (in the night)
- Staging
- Delivery of 50 datenklos
- Delivery telehandler: https://www.boels.nl/en/rental/aerial-platforms/telescopic-boom-lifts/telescopic-boom-lift16-m
- NOC storage available & Logistics team on-site (to be confirmed)
- Pickup of CCC flightcase (DHL)
- Tables available for NOC tent (?)
- Staging
- CCC flightcase arrives?
- NOC storage available & Logistics team on-site (to be confirmed)
- NOC tent setup
- Delivery of generators E0 + L0
- Delivery of airco's
- Build base of operations
- Transport of gear/cables to site
- NOC storage available & Logistics team on-site (to be confirmed)
- Scafftubes arrive
- Rollout orga area
- Start datenklo deployment
- Start cable deployment
-
- Fibres to DK-Uplink-*, entrance and parkinglot have priority
- POC arrives
- SysAdmin deploy servers
- Continue cable deployment
-
- Fibres to DK-Uplink-*, entrance and parkinglot have priority
- Continue cable deployment
- Start access deployment (if power is done)
-
- Entrance & parking lot have priority
- Continue access deployment
-
- Entrance & parking lot have priority
- Continue access deployment
- EOD: finish deployment
- Stuff should be done, time for relaxing
- Day 1
- Day 2
- Day 3
- Day 4
- Day 5
- Start teardown
- Teardown
- Finish NOC teardown
- Overflow
- Pickup datenklos
- Pickup of aircos
- Pickup of telehandler
- Pickup of generators
- From 17:00 - Hackaton with Cumulus gear @ Bitlair
- From 11:00 - Hackaton with Cumulus gear @ Bitlair
- From 14:00 - Orga meet @ RevSpace (NOC members also welcome and RevSpaceBBQ afterwards!) https://orga.sha2017.org/index.php/SHA2017_orga_meeting_20170624
- Cumulus hacking @ Bitlair
- Deploy uplink gear @ Nikhef (Juniper)
- NOC meeting 21:00 @ Mumble
- Fibre party @ Hack42 --> https://orga.sha2017.org/index.php/NOC_FibreSplicingParty_20170708
- Finishing up of fibres
- Testing of on-field patches, meet @ 11:30 @ Bitlair
- Staging @ Bitlair (core)
- Building of AP boxes
- Deadline for EuroFiber/Unet dark-fibre
- Deploy uplink gear @ Zeewolde, meet @ 11:30 @ Bitlair
- Deploy core-gear @ Zeewolde, meet @ 11:30 @ Bitlair
- Staging party @ Bitlair (access, WiFi)
- Staging